March 2022

Construction &
Titles Updates

Construction & Title Update

 
 
 
 
 
 
 
 

Stage 10

Phase 8: Titles Office & Settlement

Titled

 
 
 
 
 
 
 
 

Stage 11

Phase 6: Footpaths & Asphalt

August 2022

 
 
 
 
 
 
 
 

Stage 12

Phase 6: Footpaths & Asphalt

August 2022

 
 
 
 
 
 
 
 

Stage 14

Phase 4: Road boxing, Kerb & Channel

Q1 2023

 
 
 
 
 
 
 
 

Stage 15

Phase 4: Road boxing, Kerb & Channel

Q1 2023

 
 
 
 
 
 
 
 

Stage 16

Phase 3: Sewer & Drainage

Q1 2023

 
 
 
 
 
 
 
 

Stage 22

Phase 1: Plans & Permits

Q2 2023

 
 
 
 
 
 
 
 

Stage 23

Phase 7: Completion & Inspection of Works

August 2022

 
 
 
 
 
 
 
 

Stage 24A

Phase 3: Sewer & Drainage

Q1 2023

 
 
 
 
 
 
 
 

Stage 24B

Phase 3: Sewer & Drainage

Q2 2023

 
 
 
 
 
 
 
 

Stage 25

Phase 3: Sewer & Drainage

Q2 2023

 
 
 
 
 
 
 
 

Stage 26

Phase 1: Plans & Permits

Q4 2023

 
 
 
 
 
 
 
 

Stage 30

Phase 1: Plans & Permits

Q2 2023

 
 
 
 
 
 
 
 

Stage 31

Phase 1: Plans & Permits

Q3 2023

 
 
 
 
 
 
 
 

Stage 32

Phase 1: Plans & Permits

Q4 2023

We will continue to keep you updated on construction progress onsite. We note that delays can be caused by circumstances beyond our control, such as weather, but we will do all we can to minimise their impact. UPDATED: March 2022

Construction Phases

Phase 1

 

Plans & Permits

Council and Authority acceptance of documentation including engineering design to allow physical works to commence on site.

Phase 2

 

Earthworks

Preparation of the site to achieve design lot levels including site scrape, shaping of the existing ground and construction of retaining walls if required.

Phase 3

 

Sewer & Drainage

Installation of sewer and drainage to service the development of the stage.

Phase 4

 

Road boxing, Kerb & Channel

Prepare the ground and start to construct the lower layers of the road pavement. Install water and gas mains and construct kerb and channel.

Phase 5

 

Electrical & Telecommunications

Trench and install electrical and telecommunication services once kerb and channel works are complete.

Phase 6

 

Footpaths & Asphalt

Prepare the ground in readiness to construct footpaths. Construct footpaths and topsoil nature strips. Construction of middle pavement layers and placement of asphalt.

Phase 7

 

Completion & Inspection of Works

Council and Service Authority works inspections and sign off to constructed works including roads and services. Provision of all documentation to Council to facilitate a Statement of Compliance for the development stage.

Phase 8

 

Titles Office & Settlement

Registration of individual lots from each stage occurs at the titles office, and your block is now ready for you to settle & start the construction of your new home. Congratulations!